Pour a small concrete pad
A level slab for a grill, trash cans or a small shed. Bagged concrete, no truck.
How big is the pad?
This one needs a trailer
Before you start
How it goes · about a weekend · some experience
- Mark the pad, dig out 8 in, and tamp the ground flat and firm.
- Screw the 2×4 forms together around the hole, stake them every 2 ft, and set them level with a slight fall away from any building.
- Fill 4 in of paver base inside the forms and tamp it hard.
- Lay the rebar in a grid on the chairs so it sits in the middle of the slab, and tie the crossings with wire.
- Mix the concrete a few bags at a time to a thick oatmeal texture and fill the forms, working it into the corners.
- Drag a straight 2×4 across the forms to level it, float it smooth once the surface water is gone, and run the edger around the sides.
- Keep it damp and covered for three days, and stay off it for a week.